UPDATE ON THE ELECTRICITY/POWER SITUATION IN BAYELSA STATE from the office of Technical Adviser to the Executive Governor of Bayelsa State on Print Media/Public Affairs.

1. 19 OF THE 132KV TOWERS THAT COLLAPSED HAVE BEEN RE-ERECTED OVER 3 WEEKS AGO.

2. RESTRINGING WORK ON THE 16 TOWERS ALONG AHOADA-OKOGBE AXIS AND 3 AT IGBOGENE ARE 100% COMPLETED

3. THE 29-31 TOWERS LINES THAT WERE HEALTHY BUT WERE VANDALIZED LAST WEEK HAVE BEEN HANDLED AND EVERYTHING IS PERFECT NOW.

• REMARK

ALL WORKS HAVE BEEN COMPLETED.

• NEXT LINE OF ACTION

1. JOINT PATROL/INSPECTION OF THE COMPLETED LINES (WORK) BY THE TEAM FROM BAYELSA STATE ELECTRICITY COMPANY LIMITED AND THE TRANSMISSION COMPANY OF NIGERIA (TCN). THEY WILL MOVE ALONG THE LINES FROM AHOADA TO IGBOGENE TO RECONFIRM AND CERTIFY THE JOB WELL DONE.

2. COMMISSIONING/POWERING OF LINE. THE MOMENT THE INSPECTION IS DONE, THE LINES WILL BE POWERED IMMEDIATELY.

• TIME TO EXPECT ELECTRICITY/POWER IN BAYELSA STATE

ALL THINGS BEEN EQUAL, ELECTRICITY/POWER WILL BE RESTORED TO BAYELSA STATE HOPEFULLY WITHIN THIS VERY WEEK.

APPRECIATION

We thank Almighty God for His grace upon our Miracle and Prosperity Gov. Douye Diri and his very trusted and dependable Deputy, His Excellency Senator Lawrence Ewhrudjakpo and His faithfulness to the ASSURED PROSPERITY TEAM.

We thank His Excellency Senator Douye Diri for his love and service to Bayelsa state and Bayelsans.

Above all, we thank His Excellency for providing all the resources that were needed for the herculean project.

We thank the Honourable Commissioner of Power and the very outstanding Commissioner of Information and Strategy for their immeasurable sacrifices and commitment to the restoration of Power to Bayelsa State.

We extend same token to the Technical Adviser to the Governor on Power.

Here, we must give special honour, commendation and appreciation to Engr. Olice Kemenanabo, the Managing Director/CEO of Bayelsa State Electricity Company Limited for his unquantifiable sacrifices.

If majority of public servants can show this level of passion, fidelity, commitment, devotion and dedication to their principals and duty, we shall have a better society.

The biggest, greatest and most powerful Masquerades always come last during masquerade displays and dances.

Bayelsans and other residents and visitors are the biggest, greatest and most powerful Masquerades here and they deserve the highest Encomium and Appreciation for their understanding, patience and cooperation.

Finally, the days, weeks and months of waiting are over.

Cheerfully, what appeared as an ugly and painful experience has resulted to a positive omen.

The ASSURED PROSPERITY ADMINISTRATION has commissioned the building of a Brand New Independent Power Plant so that Bayelsa State can have uninterrupted Power.

We are marching towards a New Dawn. All the government need is your usual support.

Reported by Hon. Wisdom Oniekpar Ikuli, Technical Adviser to the Executive Governor of Bayelsa State on Print Media/Public Affairs.

Back to top button